2018 Construction Season

Below are some of our Internet expansion and improvement areas for the 2018 construction season.  While we strive to complete all of these projects in our limited construction season, unforeseen circumstances such as emergency repairs, forces of nature and other weather related issues can delay or prevent us from reaching our seasonal goals.

If you’re interested in better service at your location, please complete this form as it helps us plan for future improvements.

 

Colgate South West

Fiber to the home, approximately 7 customers. Start point, south of Colgate going west, south west, roughly 8 miles of fiber optic cable

Dazey East

Fiber to the home, approximately 18 customers. Starting from our Dazey central office going north, then east, roughly 13 miles of fiber optic cable

 

Dazey East Phase II

Fiber to the home, approximately 24 customers. Start point 115th Ave SE and 16th St SE, going north, south and east, roughly 18 miles of fiber optic cable

 

Dazey North West

Fiber to the home, approximately 20 customers. Starting at our central office in Dazey going north, north west, roughly 20 miles of fiber optic cable

 

Fingal North

Fiber to the home, approximately 10 customers. Start point north of Fingal, going north, roughly 7 miles of fiber optic cable

 

Hope North East

Fiber to the home, approximately 20 customers. Start point north east of Hope going north, north east, roughly 19 miles of fiber optic cable

 

Hope South East

Fiber to the home, approximately 20 customers. Start point north east of Hope, going east, south east, roughly 27 miles of fiber optic cable

 

Page South West

Fiber to the home, approximately 7 customers. Start point 18th St SE and 133rd Ave SE, going south, roughly 7 miles of fiber optic cable

 

Sanborn South Phase II

Fiber to the home, approximately 14 customers. Start point one mile south of I-94 on 104th Ave SE, going south west roughly 20 miles of fiber optic cable