2017 Construction Season

Below are some of our Internet expansion and improvement areas for the 2017 construction season.  While we strive to complete all of these projects in our limited construction season, unforeseen circumstances such as emergency repairs, forces of nature and other weather related issues can delay or prevent us from reaching our seasonal goals.

If you’re interested in better service at your location, please complete this form as it helps us plan for future improvements.

 

Alice East

Fiber to the home, approximately 13 customers, one tower site. Start point out of the Alice central office building going south east, roughly 14 miles of fiber optic cable

Fingal West

Fiber to the home, approximately 13 customers, start point out of the Nome central office building going north, northwest, roughly 22 miles of fiber optic cable

 

 

Sanborn South

Fiber to the home, approximately 15 customers. Start point south of I-94 south of Sanborn, heading south, roughly 12 miles of fiber optic cable

 

Urbana to Eckelson

Fiber to the home along route approximately 8 customers, and roughly 6 miles of fiber optic cable starting from Eckelson

 

 

 

Wheatland Southwest

One tower site. Starting a mile west of Wheatland going south west, roughly 4 miles of fiber optic cable